Can't deselect all projects at once in template task assignment dialog
The dialog where you assign a template task to projects has changed. You can now filter by tags - yay! But I can no longer deselect all projects to unassign them at once. I can check the top box next to Project and it shows everything on the current page being selected, and when I check it again, everything I can see deselects. Unfortunately, when I try to apply the change, I get a message that "Tasks failed to update". The effect of this in my organization is that we have to go through 38 pages of projects to unassign
-
Task Timeline not shown
Hello,
The Task Timeline is not showing scheduled Tasks. I select a day, hit View and nothing shows. Not sure if there is an issue with how I set up the tasks or something else.
I would like to schedule the tasks to be run at night but am unable to do so.
Support would be helpful.
Thanks,
Bruce Gunderson