How often should model metrics tasks run?

We'd like to get an opinion as to how often should model metrics run on models? I am thinking this task should run on weekends because of the complexity of the task. Any thoughts or ideas are welcomed.

Thank you,

1 reply

Miguel - I'll be interested to hear what other users have to say about this... I think it somewhat depends on how often you'd like to check on the metrics - or what kind of interval it makes sense to see the data in.  If you were interested about "when did someone add a bunch of warnings to the model" - is it good enough to know what week it happened?

In my experience it is not a task that's very complex. But still - it does have to open the model to do the job.

I do know that some people that run it more often - but in some cases they change the priority to a lower number, so that if there are PDFs or other deliverables in the queue, those should run first.