Hot Topics

  • 1

    Can't deselect all projects at once in template task assignment dialog

    Tiffany Guthrie · 1 · Last reply by Mandi Bishop

    The dialog where you assign a template task to projects has changed. You can now filter by tags - yay! But I can no longer deselect all projects to unassign them at once. I can check the top box next to Project and it shows everything on the current page being selected, and when I check it again, everything I can see deselects. Unfortunately, when I try to apply the change, I get a message that "Tasks failed to update". The effect of this in my organization is that we have to go through 38 pages of projects to unassign

  • 1

    Task Timeline not shown

    Bruce Gunderson II · 0 · Posted

    Hello,

    The Task Timeline is not showing scheduled Tasks. I select a day, hit View and nothing shows. Not sure if there is an issue with how I set up the tasks or something else.

    I would like to schedule the tasks to be run at night but am unable to do so.

    Support would be helpful.

    Thanks,

    Bruce Gunderson

  • 1

    Autodesk Vault connect support

    Bruce Gunderson II · 0 · Posted

    Hello,

    We have Autodesk Vault for Revit document control. We would like to connect to Vault Server and the files in Vault in order to run Tasks. It would be great to have a connect to Vault similar to Projectwise.

    Thanks,

    Bruce Gunderson